SiteProof · Project Intelligence MARSA BAY — Package 02 · auto-updated daily
★ PREMIUM
Period:
Discipline: All Unit: U340 Party: DCC Updated: 04 Jun 2026, 18:00
Workforce (today)
1,860
▲ +2.4%
Cranes
16
▲ stable
Pours (period m³)
258
▲ +14%
Open issues
6
▲ 2 new
Reports approved
9/10
90%
Indirect ratio
7.3%
193 staff

Manpower trend

Daily on-site workforce — 10-day window
23May28May04Jun

Discipline split

Direct workforce by trade group
1,860direct
Civil 31%Scaffold 21%Piping 18%Steel 15%E&I 15%

Concrete pours per day

m³ poured · period
33
26
9
27
96
31
7.5
01
15
02
72
03

Equipment utilization

Top equipment · count
Cranes
16
Generators
14
Dump trucks
12
Bobcat
12
Man lift
10

Open-issue aging

Days open (red = ageing)
STR-7101 redline
5d
PIB-24 CMU lap
3d
U370 permit hold
1d
Rigger L1 (nights)
2d
Ceramic delivery
2d

Recent daily reports

Status & key numbers
DateWorkforcePours m³IssuesStatus
04 Jun1,860724Draft
03 Jun1,860724Approved
02 Jun2,57603Approved
01 Jun2,60302Approved
31 May7.53Approved

Photo evidence

Latest site photos (auto-tagged)
STR-1000 pour
U370 permit hold
340-C-6021 lift
CMU lap NCR
Duct bank
⭐ NEXUS insight: U340 CLD formwork ready 4 days, awaiting DCC — flag for commercial review.